Ensco - 71

Rigfit7Seas were contracted by Ensco to carry out an accommodation upgrade for Ensco 71.

The scope of the project was to bring the POB from its current maximum capacity of 80 up to 98. This was achieved by fabricating, outfitting and installing an additional three level bespoke accommodation block.

A crew of 50 persons worked on the project for around 120 days based out of the Rigfit7Seas base in the Hamriyah free Zone 1,UAE.